September 19, 2017

After a full week of work following Hurricane Irma, we are beginning to get back to a state of normalcy at the resort. Clean up and repair is still ongoing, as we had still been recovering from Hurricane Matthew before Irma graced us with her presence. 

To date, th...

September 14, 2017

Just a quick note: We are still working hard on getting the resort back up and operational but there is a lot of work to be done before the resort can open to owners and guests. 

We have been contacting our third-party service providers daily to get an estimated ti...

September 13, 2017

We are in day two of hard work at the Silver Beach Club with cleaning up after Hurricane Irma. It has been a long two days, but progress is being made.  The sun is shining and we are all extremely grateful that the storm spared us from the extreme damage seen in other...

September 12, 2017

Members of the Silver Beach Club Staff were able to get to the building this morning as the bridges were closed yesterday until later on in the evening. Staff is still assessing damages from Hurricane Irma. Once the building has been thoroughly inspected a representati...

January 20, 2017

We are so happy to announce that we are open for business again! We are still working on the property and some floors are still closed to guests for safety reasons, but we have had two mostly successful weeks with guests on site. 

We want to stress that a lot of work is...

December 30, 2016

2016 is rapidly coming to a close and we are looking towards 2017 as a year of positive change and growth at Silver Beach Club. This has been an interesting year full of unexpected events that has catapulted us into making some very big moves to improve the property.

Si...

December 14, 2016

Yesterday our order of porcelain tile was delivered to the resort. Contractors are currently removing old tile and prepping rooms for immediate installation. The interior rooms are all being painted and units with popcorn ceilings are being scraped, texturized and pain...

November 18, 2016

There is not a whole lot to report on this week; however, progress is being made. Over the last 7 days, we started interior work in the units, ordered some new sleeper sofas, and began receiving bids for new flooring. We are awaiting more information from contractors a...

November 11, 2016

We know. We hear you. Everyone wants to know exactly what's happening over at Silver Beach Club after the storm. You saw the news as the storm passed over and now that there's no more meteorological activity it seems like everything should be back to normal. We wish th...

Please reload

Featured Posts

I'm busy working on my blog posts. Watch this space!

Please reload

Recent Posts

September 12, 2017